Grading - Route 560 River de Chute Area Realignment
Federal contribution
$251,290
Federal share50%
of $502.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 22, 2019
Built
Approved 2 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- New Brunswick Department of Transportation and Infrastructure
- Construction start
- Sep 16, 2019(actual)
- Construction end
- Nov 11, 2019(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jul 29, 2019
- Construction end6 weeks lateforecast Sep 30, 2019
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54442 in the federal list. How to read these figures.