Grading - Route 560 River de Chute Area Realignment

River De Chute, New Brunswick

completeHighways and RoadsRNIS
Federal contribution
$251,290
Federal share50%

of $502.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 22, 2019
Built

Approved 2 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Sep 16, 2019(actual)
Construction end
Nov 11, 2019(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jul 29, 2019
  • Construction end6 weeks lateforecast Sep 30, 2019