Large Culvert Replacement - Red Head Road Culvert No.2 at Mispec Beach Outlet
Federal contribution
$170,131
Federal share50%
of $340.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 14, 2019
2020
Built
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- New Brunswick Department of Transportation and Infrastructure
- Construction start
- Jul 13, 2020(actual)
- Construction end
- Aug 6, 2020(actual)
Against the original forecast
- Construction start8 weeks lateforecast May 18, 2020
- Construction end3 months earlyforecast Oct 30, 2020
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54444 in the federal list. How to read these figures.