Back to projects

Large Culvert Replacement - Red Head Road Culvert No.2 at Mispec Beach Outlet

Mispec, New Brunswick

completeHighways and RoadsRNIS
Federal contribution
$170,131
Federal share50%

of $340.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 14, 2019
2020
Built
Program
Rural & Northern Infrastructure Stream
Construction start
Jul 13, 2020(actual)
Construction end
Aug 6, 2020(actual)

Against the original forecast

  • Construction start8 weeks lateforecast May 18, 2020
  • Construction end3 months earlyforecast Oct 30, 2020

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54444 in the federal list. How to read these figures.