Paving - Route 590, Estey Road Area toward Hydroline

Waterville, New Brunswick

completeHighways and RoadsRNIS
Federal contribution
$564,795
Federal share50%

of $1.1M total eligible cost; the rest comes from other partners.

Approved 2 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Sep 16, 2019(actual)
Construction end
Oct 14, 2019(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jul 29, 2019