Paving - Route 108 from Bryenton Area toward Parker Road
Federal contribution
$340,935
Federal share50%
of $681.9K total eligible cost; the rest comes from other partners.
Approved 4 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- New Brunswick Department of Transportation and Infrastructure
- Construction start
- Aug 26, 2019(actual)
- Construction end
- Oct 2, 2019(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jul 29, 2019
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54446 in the federal list. How to read these figures.