Schedule

Announced and approvedAug 19, 2019
2020
Built

Approved 3 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Sep 9, 2020(actual)
Construction end
Sep 16, 2020(actual)

Against the original forecast

  • Construction start2 months lateforecast Jul 1, 2020
  • Construction end6 weeks earlyforecast Oct 31, 2020