The Epekwitk Mena'taqug Centre
Scotchfort, Prince Edward Island
Federal contribution
$816,000
Federal share75%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 30, 2019
2020202120222023
Built
Approved 3 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Abegweit First Nation
- Construction start
- Jun 15, 2021(actual)
- Construction end
- Nov 28, 2022(actual)
Against the original forecast
- Construction start7 weeks lateforecast Apr 30, 2021
- Construction end4 months lateforecast Jul 15, 2022
Also in Scotchfort