Flood Mitigation - Upsalquitch River Road
Federal contribution
$1.2M
$1,160,000
Federal share67%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 29, 2019
2020202120222023
Built
Approved 2 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- New Brunswick Department of Transportation and Infrastructure
- Construction start
- Aug 3, 2022(actual)
- Construction end
- May 29, 2023(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jul 18, 2022
- Construction end2 weeks earlyforecast Jun 15, 2023
Also in Undefined
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54490 in the federal list. How to read these figures.