Flood Mitigation - Upsalquitch River Road

Undefined, New Brunswick

completeDisaster MitigationGIS
Federal contribution
$1.2M
$1,160,000
Federal share67%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 29, 2019
2020202120222023
Built

Approved 2 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Aug 3, 2022(actual)
Construction end
May 29, 2023(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jul 18, 2022
  • Construction end2 weeks earlyforecast Jun 15, 2023

Also in Undefined

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54490 in the federal list. How to read these figures.