Town of Rouleau and Village of Wilcox Regional Water System
Federal contribution
$4.2M
$4,242,300
Federal share40%
of $10.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2019
20202021202220232024
Built
Approved 3 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Rouleau & Village of Wilcox
- Construction start
- Jul 20, 2020(actual)
- Construction end
- Mar 31, 2024(actual)
Against the original forecast
- Construction start4 months lateforecast Mar 31, 2020
- Construction end12 months lateforecast Mar 31, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54504 in the federal list. How to read these figures.