Replacement of Tecumseth Road Culvert
Walpole Island First Nation, Ontario
Federal contribution
$419,939
Federal share75%
of $559.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 24, 2020
today
2020202220242026
BuiltForecast
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Walpole Island First Nation
- Construction start
- Jun 1, 2026(forecast)
- Construction end
- Sep 30, 2026(forecast)
Also in Walpole Island First Nation