Dillon Road Improvements

Carling, Ontario

completeHighways and RoadsRNIS
Federal contribution
$2.1M
$2,109,330
Federal share60%

of $3.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 14, 2020
20212022
Built

Approved 2 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Carling
Construction start
Mar 8, 2022(actual)
Construction end
Nov 1, 2022(actual)

Against the original forecast

  • Construction start7 months lateforecast Aug 3, 2021