Improvements to Two Roads in Sheshagwaning First Nation
Sheshegwaning First Nation, Ontario
Federal contribution
$816,750
Federal share75%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 25, 2020
2021
Built
Approved 3 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Sheshegwaning River First Nation
- Construction start
- Aug 1, 2020(actual)
- Construction end
- Nov 5, 2021(actual)
Against the original forecast
- Construction end3 weeks earlyforecast Nov 26, 2021
Also in Sheshegwaning First Nation
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54578 in the federal list. How to read these figures.