Improvements to Two Roads in Sheshagwaning First Nation

Sheshegwaning First Nation, Ontario

completeHighways and RoadsRNIS
Federal contribution
$816,750
Federal share75%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 25, 2020
2021
Built

Approved 3 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Aug 1, 2020(actual)
Construction end
Nov 5, 2021(actual)

Against the original forecast

  • Construction end3 weeks earlyforecast Nov 26, 2021