Back to projects

Construction of the Former Welland Canal Crossing

Welland, Ontario

completeHighways and RoadsRNIS
Federal contribution
$2.5M
$2,499,750
Federal share50%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2020
2021202220232024
Built

Approved 2 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
City of Welland
Construction start
Dec 12, 2022(actual)
Construction end
Aug 16, 2024(actual)

Also in Welland