Lakeview Bridge Replacement
Federal contribution
$1.2M
$1,178,700
Federal share60%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 25, 2020
202120222023
Built
Approved 2 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Township of Laird
- Construction start
- Jul 5, 2021(actual)
- Construction end
- Dec 31, 2022(actual)