Reconstruction of Bridge 24 over the Nith River
Federal contribution
$2.0M
$1,968,750
Federal share50%
of $3.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 6, 2020
today
2021202320252027
BuiltForecast
Approved 3 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Township of Blandford-Blenheim
- Construction start
- Sep 8, 2026(forecast)
- Construction end
- May 28, 2027(forecast)
Also in Blandford-Blenheim
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54595 in the federal list. How to read these figures.