Upgrade of the Moyer's Bridge and Reconstruction of McLean Road
Federal contribution
$398,010
Federal share50%
of $796.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2020
2021
Built
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Township of Puslinch
- Construction start
- Aug 24, 2020(actual)
- Construction end
- Jun 18, 2021(actual)
Against the original forecast
- Construction end2 months earlyforecast Aug 27, 2021
Also in Puslinch
- Puslinch Community Centre Renovation and Upgrade$793.4K
- Replacement of the Lights and Upgrading of the Washrooms at the Old Morriston Park$113.3K
- Township Storage Building$91.0K
- Renovations and Modifications to Municipal Office$80.0K
- Study for the Implementation of a Municipal Drinking Water Well System and Associated Services$37.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54634 in the federal list. How to read these figures.