Reconstruction of Nawash Unceded First Nation Roads and Culverts

Chippewas of Nawash Unceded First Nation, Ontario

underwayHighways and RoadsRNIS
Federal contribution
$3.1M
$3,143,700
Federal share75%

of $4.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2020
today
202120222023202420252026
BuiltForecast

Approved 2 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Apr 6, 2026(actual)
Construction end
Sep 25, 2026(forecast)

Against the original forecast

  • Construction start7 months lateforecast Sep 15, 2025

Also in Chippewas of Nawash Unceded First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54645 in the federal list. How to read these figures.