Back to projects

Juan de Fuca Arena Improvement

Colwood, British Columbia

completeRecreationCCRIS
Federal contribution
$798,936
Federal share40%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 6, 2019
202020212022
Built
Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Feb 2, 2021(actual)
Construction end
Jun 10, 2022(actual)

Also in Colwood