Back to projects

Conventional Fleet Replacement

Barrie, Ontario

underwayPublic TransitPTIS
Federal contribution
$9.4M
$9,355,609
Federal share40%

of $23.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 13, 2020
today
202020222024202620282030
BuiltForecast

Approved 10 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of Barrie
Construction start
Jul 13, 2020(actual)
Construction end
Dec 31, 2029(forecast)

Also in Barrie