Transit Upgrades and Fleet Replacement
Federal contribution
$1.2M
$1,248,670
Federal share40%
of $3.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 28, 2020
today
20202023202620292032
BuiltForecast
Approved 4 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Temiskaming Shores
- Construction start
- May 11, 2020(actual)
- Construction end
- Oct 31, 2033(forecast)
Also in Temiskaming Shores
- Building a Net-Zero Indigenous Community Gathering Space in Northern Ontario$2.7M
- Temiskaming Shores Infrastructure Upgrades, Phase 1$2.1M
- Waterfront Pool & Fitness Centre Energy & GHG Retrofit$810.2K
- Highway Resurfacing - New Liskeard and Cochrane Regions$500.0K
- Replacement of Existing Iron Removal Filters at the McCamus Avenue Water Treatment Plant$344.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55103 in the federal list. How to read these figures.