Bus Pad and Shelter Replacement

Brantford, Ontario

completePublic TransitPTIS
Federal contribution
$330,000
Federal share49%

of $676.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2020
202120222023
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of Brantford
Construction start
May 1, 2020(actual)
Construction end
Jun 30, 2023(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Apr 1, 2020

Also in Brantford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55126 in the federal list. How to read these figures.