Mobility Systems Hardware
Federal contribution
$179,628
Federal share40%
of $449.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 27, 2020
202120222023
Built
Approved 4 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Corporation of the City of Thunder Bay
- Construction start
- Oct 20, 2020(actual)
- Construction end
- Dec 31, 2022(actual)
Against the original forecast
- Construction start7 months lateforecast Apr 1, 2020
Also in Thunder Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55127 in the federal list. How to read these figures.