Transit Maintenance Facility Upgrades
Federal contribution
$414,000
Federal share56%
of $738.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2020
202120222023
Built
Approved 4 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Brantford
- Construction start
- Sep 14, 2021(actual)
- Construction end
- Aug 1, 2023(actual)
Against the original forecast
- Construction end5 months earlyforecast Dec 31, 2023
Also in Brantford
- Laurier Brantford YMCA Athletics and Recreation Complex$16.7M
- Construction of Wayne Gretsky Centre Four-Pad Arena$13.0M
- Upgrade of the Water Treatment Plant$5.4M
- Enclosing Open Concept Classrooms; HVAC; Water filling Station; Hallway door hold open devices; Entrance door security access$4.7M
- Grand Riverview$4.4M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55156 in the federal list. How to read these figures.