Conventional and Specialize Bus Procurement
Federal contribution
$4.0M
$3,995,200
Federal share40%
of $10.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2020
202020212022202320242025
Built
Approved 4 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Brantford
- Construction start
- Dec 1, 2020(actual)
- Construction end
- May 6, 2025(actual)
Against the original forecast
- Construction end8 months earlyforecast Dec 31, 2025
Also in Brantford
- Laurier Brantford YMCA Athletics and Recreation Complex$16.7M
- Construction of Wayne Gretsky Centre Four-Pad Arena$13.0M
- Upgrade of the Water Treatment Plant$5.4M
- Enclosing Open Concept Classrooms; HVAC; Water filling Station; Hallway door hold open devices; Entrance door security access$4.7M
- Grand Riverview$4.4M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55211 in the federal list. How to read these figures.