underwayDisaster MitigationDMAF
Federal contribution
$17.9M
$17,949,080
Federal share40%

of $44.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 6, 2019
today
20192021202320252027
BuiltForecast
Program
Disaster Mitigation and Adaptation Fund
Ultimate recipient
City of Deux-Montagnes
Construction start
Jan 4, 2019(actual)
Construction end
Jul 1, 2028(forecast)

Against the original forecast

  • Construction start19 months earlyforecast Aug 1, 2020