Yonge North Subway Extension
Federal contribution
$797.1M
$797,137,038
Federal share20%
of $4.1B total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 11, 2021
ApprovedFeb 24, 2025
2022202320242025
The source gives no usable construction span.
Approved 3.8 years after the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Metrolinx
- Construction start
- Aug 28, 2025(actual)
- Construction end
- —(forecast)
Against the original forecast
- Construction start2.7 years lateforecast Jan 1, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56155 in the federal list. How to read these figures.