Alexis Creek First Nation - Cultural Youth Centre Renovation and Addition

Alexis Creek, British Columbia

completeCultureCCRIS
Federal contribution
$254,437
Federal share75%

of $339.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2020
2020
Built

Approved 7 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Jan 6, 2020(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Nov 29, 2019

Also in Alexis Creek

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56180 in the federal list. How to read these figures.