East Kootenay - Edgewater Connectivity
East Kootenay, British Columbia
Federal contribution
$491,400
Federal share60%
of $819.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
2020202220242026
BuiltForecast
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Regional District of East Kootenay
- Construction start
- Dec 2, 2025(forecast)
- Construction end
- Apr 30, 2026(forecast)