Kitsumkalum Indian Band - Community Hall Upgrades
Kitsumkalum Indian Reserve, British Columbia
Federal contribution
$1.8M
$1,808,491
Federal share75%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
today
2021202320252027
BuiltForecast
Approved 2 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Kitsumkalum Indian Band
- Construction start
- Aug 6, 2024(actual)
- Construction end
- Mar 31, 2027(forecast)
Against the original forecast
- Construction start6 weeks lateforecast Jun 28, 2024
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56281 in the federal list. How to read these figures.