Gibsons - White Tower Stormwater Pond
Federal contribution
$573,000
Federal share60%
of $955.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
2021202220232024
Built
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Gibsons
- Construction start
- Oct 16, 2023(actual)
- Construction end
- May 31, 2024(actual)
Against the original forecast
- Construction start8 months lateforecast Mar 1, 2023
- Construction end6 months lateforecast Dec 15, 2023