Nisga'a Village of Gitwinksihlkw - Ts'oohl Ts'ap Recreation Centre Upgrade
Nisgaa Village of Gitwinksihlkw, British Columbia
Federal contribution
$2.1M
$2,100,484
Federal share75%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
2021
Built
Approved 2 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Nisga'a Village of Gitwinksihlkw
- Construction start
- Jul 29, 2020(actual)
- Construction end
- Jun 11, 2021(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2020
- Construction end4 months lateforecast Feb 12, 2021
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56290 in the federal list. How to read these figures.