Skowkale First Nation - SAY Community Centre
Skowkale IR#10, British Columbia
Federal contribution
$4.0M
$3,964,230
Federal share75%
of $5.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
20212022
Built
Approved 8 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Skowkale First Nation
- Construction start
- Jun 23, 2020(actual)
- Construction end
- Oct 6, 2022(actual)
Against the original forecast
- Construction start4 months lateforecast Mar 2, 2020
- Construction end10 months lateforecast Dec 10, 2021
Also in Skowkale IR#10