Doig River First Nation - Tea Dance Circle

Doig River First Nation, British Columbia

completeCultureCCRIS
Federal contribution
$906,750
Federal share75%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2020
2021
Built

Approved 3 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Doig River First Nation
Construction start
Nov 2, 2020(actual)
Construction end
May 31, 2021(actual)

Against the original forecast

  • Construction start5 months lateforecast Jun 1, 2020
  • Construction end5 months lateforecast Dec 18, 2020

Also in Doig River First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56294 in the federal list. How to read these figures.