Telkwa - WWTP and Sanitary Collection System Rehabilitation
Federal contribution
$1.4M
$1,446,375
Federal share60%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
20212022202320242025
Built
Approved 2 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Village of Telkwa
- Construction start
- Apr 5, 2021(actual)
- Construction end
- Nov 16, 2024(actual)
Against the original forecast
- Construction end3 weeks earlyforecast Dec 6, 2024
Also in Telkwa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56299 in the federal list. How to read these figures.