Back to projects

Water Systems Upgrades

Saint-Ferréol-les-Neiges, Quebec

completeWastewaterGIS
Federal contribution
$548,050
Federal share40%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 4, 2020
20212022
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Saint-Férréol-les-Neiges
Construction start
May 17, 2021(actual)
Construction end
Oct 13, 2022(actual)

Against the original forecast

  • Construction end12 months lateforecast Sep 29, 2021

Also in Saint-Ferréol-les-Neiges