Water Systems Upgrades
Saint-Ferréol-les-Neiges, Quebec
Federal contribution
$548,050
Federal share40%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2020
20212022
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Saint-Férréol-les-Neiges
- Construction start
- May 17, 2021(actual)
- Construction end
- Oct 13, 2022(actual)
Against the original forecast
- Construction end12 months lateforecast Sep 29, 2021
Also in Saint-Ferréol-les-Neiges
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56301 in the federal list. How to read these figures.