Southern Stl'atl'imx Health Centre Refurbishment
Stl'atl'imx First Nation, British Columbia
Federal contribution
$268,815
Federal share75%
of $358.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
2021
Built
Approved 4 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Southern Stl'atl'imx Health Society
- Construction start
- Oct 5, 2020(actual)
- Construction end
- Mar 31, 2021(actual)
Against the original forecast
- Construction start6 months lateforecast Apr 1, 2020
- Construction end10 months earlyforecast Jan 31, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56312 in the federal list. How to read these figures.