Central Coast Regional District - Great Bear Playgrounds
Bella Coola Valley, British Columbia
Federal contribution
$541,593
Federal share60%
of $902.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
2020202220242026
BuiltForecast
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Central Coast Regional District
- Construction start
- Jun 19, 2024(actual)
- Construction end
- Dec 1, 2025(forecast)
Against the original forecast
- Construction start3 months lateforecast Apr 1, 2024
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56315 in the federal list. How to read these figures.