Toquaht Nation - t¿uk¿¿aa¿ath¿iic his¿imyily¿ak - Toquaht Gathering Place

Toquaht Nation, British Columbia

completeCultureRNIS
Federal contribution
$1.2M
$1,248,000
Federal share75%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2020
20212022
Built

Approved 2 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Toquaht Nation
Construction start
Jun 8, 2020(actual)
Construction end
Nov 21, 2022(actual)

Against the original forecast

  • Construction start3 months lateforecast Mar 1, 2020
  • Construction end9 months lateforecast Feb 28, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56324 in the federal list. How to read these figures.