Back to projects

Water Systems Upgrade

Saint-Hilarion, Quebec

completeWastewaterGIS
Federal contribution
$222,507
Federal share40%

of $556.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 4, 2020
2021
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Construction start
May 10, 2021(actual)
Construction end
Aug 26, 2021(actual)

Also in Saint-Hilarion