Water Systems Upgrades
Federal contribution
$719,125
Federal share40%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2020
202120222023
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Château-Richer
- Construction start
- May 19, 2020(actual)
- Construction end
- Dec 31, 2022(actual)
Against the original forecast
- Construction start12 months earlyforecast Jun 1, 2021