Water Systems Upgrades

Saint-Basile, Quebec

completeWastewaterGIS
Federal contribution
$109,102
Federal share40%

of $272.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 4, 2020
20212022
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Saint-Basile
Construction start
Aug 8, 2022(actual)
Construction end
Oct 14, 2022(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jun 30, 2022
  • Construction end6 weeks lateforecast Aug 30, 2022