Water Systems Upgrades
Federal contribution
$109,102
Federal share40%
of $272.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2020
20212022
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Saint-Basile
- Construction start
- Aug 8, 2022(actual)
- Construction end
- Oct 14, 2022(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jun 30, 2022
- Construction end6 weeks lateforecast Aug 30, 2022
Also in Saint-Basile
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56357 in the federal list. How to read these figures.