Water systems upgrade

Saint-Gabriel, Quebec

completeWastewaterGIS
Federal contribution
$2.0M
$1,980,340
Federal share40%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 17, 2020
202120222023
Built

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Saint-Gabriel
Construction start
May 31, 2021(actual)
Construction end
Mar 23, 2023(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Apr 26, 2021
  • Construction end9 months lateforecast Jun 30, 2022

Also in Saint-Gabriel

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56360 in the federal list. How to read these figures.