Schedule
Announced and approvedSep 15, 2020
2021
Built
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Saint-Elphège
- Construction start
- May 1, 2021(actual)
- Construction end
- Oct 28, 2021(actual)
Against the original forecast
- Construction start7 months lateforecast Oct 14, 2020
- Construction end4 months lateforecast Jun 30, 2021