Back to projects

Water Systems Upgrades

Saint-Éphrem-de-Beauce, Quebec

completeWastewaterGIS
Federal contribution
$348,750
Federal share40%

of $871.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
20212022
Built

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Saint-Éphrem-de-Beauce
Construction start
Jun 21, 2021(actual)
Construction end
Dec 31, 2021(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 1, 2021
  • Construction end3 months lateforecast Sep 30, 2021

Also in Saint-Éphrem-de-Beauce

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56371 in the federal list. How to read these figures.