Water Systems Upgrades

Saint-Agapit, Quebec

completeWastewaterGIS
Federal contribution
$395,410
Federal share40%

of $988.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
202120222023
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Saint-Agapit
Construction start
Jun 5, 2023(actual)
Construction end
Oct 16, 2023(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 1, 2023