Back to projects

West Moberly First Nations - Culture/Community Centre

West Moberly First Nations, British Columbia

completeCultureRNIS
Federal contribution
$334,170
Federal share75%

of $445.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2020
20212022
Built

Approved 4 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
West Moberly First Nations
Construction start
Dec 15, 2021(actual)
Construction end
Oct 31, 2022(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Nov 17, 2021
  • Construction end9 months lateforecast Jan 31, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56386 in the federal list. How to read these figures.