Back to projects

Nuxalk Nation - Nuxalk Bighouse

Bella Coola 1, British Columbia

approvedCultureCCRIS
Federal contribution
$3.6M
$3,569,173
Federal share75%

of $4.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2020
today
20202022202420262028
BuiltForecast

Approved 3 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Nuxalk Nation
Construction start
Jun 1, 2026(forecast)
Construction end
Nov 30, 2027(forecast)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56388 in the federal list. How to read these figures.