Back to projects

Yale First Nation - Recreation Centre

Yale First Nation, British Columbia

underwayRecreationRNIS
Federal contribution
$2.9M
$2,906,988
Federal share75%

of $3.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2020
today
2021202320252027
BuiltForecast

Approved 6 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Yale First Nation
Construction start
Dec 1, 2020(actual)
Construction end
Mar 31, 2027(forecast)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56392 in the federal list. How to read these figures.