Prophet River First Nation - Ice Rink Facility
Prophet River First Nation, British Columbia
Federal contribution
$1.9M
$1,895,662
Federal share75%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
202120222023
Built
Approved 6 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Prophet River First Nation
- Construction start
- Sep 7, 2021(actual)
- Construction end
- Aug 23, 2023(actual)
Against the original forecast
- Construction start6 months lateforecast Feb 26, 2021
- Construction end9 months lateforecast Nov 30, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56393 in the federal list. How to read these figures.