Prophet River First Nation - Ice Rink Facility

Prophet River First Nation, British Columbia

completeRecreationRNIS
Federal contribution
$1.9M
$1,895,662
Federal share75%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2020
202120222023
Built

Approved 6 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Prophet River First Nation
Construction start
Sep 7, 2021(actual)
Construction end
Aug 23, 2023(actual)

Against the original forecast

  • Construction start6 months lateforecast Feb 26, 2021
  • Construction end9 months lateforecast Nov 30, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56393 in the federal list. How to read these figures.