Maaqutusiis Hahoulthee Stewardship Society Matsquiaht Dock Project, Meares Island, Clayoquot Sound
Meares Island, British Columbia
Federal contribution
$409,090
Federal share75%
of $545.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
202120222023
Built
Approved 3 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Maaqutusiis Hahoulthee Stewardship Society
- Construction start
- Jun 20, 2022(actual)
- Construction end
- May 25, 2023(actual)
Against the original forecast
- Construction start7 weeks lateforecast Apr 30, 2022
- Construction end6 months lateforecast Nov 30, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56394 in the federal list. How to read these figures.