Saulteau First Nations - Community Cultural Building
Federal contribution
$11.7M
$11,711,907
Federal share75%
of $15.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
20212022202320242025
Built
Approved 2 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Saulteau First Nation
- Construction start
- May 16, 2022(actual)
- Construction end
- Dec 31, 2024(actual)
Against the original forecast
- Construction end4 weeks lateforecast Dec 1, 2024
Also in Chetwynd
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56433 in the federal list. How to read these figures.